Phase 1 – Automation Architecture
-Review your sequence
-Select controller platform
-Define I/O list
-Define architecture
-Define communication philosophy
Phase 2 – Hardware Selection
-PLC selection
-PC interface selection
-Stepper driver selection
-Sensor selection
-Power supply sizing
-Pneumatic component review
Phase 3 – Controls Design
-I/O mapping
-Tag list
-State machine
-Interlocks
-Fault matrix
Phase 4 – Programming
-PLC code
-PC interface software
-Modbus configuration
-Motion setup
Phase 5 – Electrical Design
-Panel layout
-Wiring diagrams
-Terminal schedule
-Power distribution
Overview:
A prototype including stepper motors, sensors and limit switches
24VDC. requirement to program, PLC, mapping, make ready to apply industry 4. in the future.
Motor drivers and all components' selections. optimizing selections to meet economic demands.
BOM and easy interface. no HMI, testing environment model.
-Review your sequence
-Select controller platform
-Define I/O list
-Define architecture
-Define communication philosophy
Phase 2 – Hardware Selection
-PLC selection
-PC interface selection
-Stepper driver selection
-Sensor selection
-Power supply sizing
-Pneumatic component review
Phase 3 – Controls Design
-I/O mapping
-Tag list
-State machine
-Interlocks
-Fault matrix
Phase 4 – Programming
-PLC code
-PC interface software
-Modbus configuration
-Motion setup
Phase 5 – Electrical Design
-Panel layout
-Wiring diagrams
-Terminal schedule
-Power distribution
Overview:
A prototype including stepper motors, sensors and limit switches
24VDC. requirement to program, PLC, mapping, make ready to apply industry 4. in the future.
Motor drivers and all components' selections. optimizing selections to meet economic demands.
BOM and easy interface. no HMI, testing environment model.
Related categories:
Wireless
Engineering
Electronics
Electrical Engineering
Programming
Control System Design
Automation
PLC