Python Scheduling Help with Question
Budget: $10 – $30 USD
Deliverables
What is the minimum total construction time? Enter your answer to the nearest day.
On what day should Interior Plumbing start to achieve the minimum construction time?
Additional Information
Reliable Construction wants to determine when each activity should start in a construction schedule in order to minimize the overall time it takes to construct a large commercial building. The tasks, order of tasks, and their durations in days are specified in the table below.
Remember that we need to append a final task that has all other tasks as immediate predecessors and an estimated duration of zero days.
Activity Description Immediate Predecessors Estimated Duration
A Excavate -- 14
B Lay the Foundation A 21
C Put up the rough wall B 63
D Put up the roof C 35
E Install the exterior plumbing C 42
F Install the interior plumbing E 56
G Put up the exterior siding D 49
H Do the exterior painting E,G 63
I Do the electrical work C 28
J Put up the wallboard F,I 35
K Install the flooring J 14
L Do the interior painting J 35
M Install the exterior fixtures H 14
N Install the interior fixtures K,L 35
What is the minimum total construction time? Enter your answer to the nearest day.
On what day should Interior Plumbing start to achieve the minimum construction time?
Must use pyomo and python and want PDF pictures of entire logic
What is the minimum total construction time? Enter your answer to the nearest day.
On what day should Interior Plumbing start to achieve the minimum construction time?
Additional Information
Reliable Construction wants to determine when each activity should start in a construction schedule in order to minimize the overall time it takes to construct a large commercial building. The tasks, order of tasks, and their durations in days are specified in the table below.
Remember that we need to append a final task that has all other tasks as immediate predecessors and an estimated duration of zero days.
Activity Description Immediate Predecessors Estimated Duration
A Excavate -- 14
B Lay the Foundation A 21
C Put up the rough wall B 63
D Put up the roof C 35
E Install the exterior plumbing C 42
F Install the interior plumbing E 56
G Put up the exterior siding D 49
H Do the exterior painting E,G 63
I Do the electrical work C 28
J Put up the wallboard F,I 35
K Install the flooring J 14
L Do the interior painting J 35
M Install the exterior fixtures H 14
N Install the interior fixtures K,L 35
What is the minimum total construction time? Enter your answer to the nearest day.
On what day should Interior Plumbing start to achieve the minimum construction time?
Must use pyomo and python and want PDF pictures of entire logic