Odoo RFQ to be generated based on Vendor Leadtime with Manufacturing involved
Budget: €8 – €30 EUR
Context:
A product (Final1) is composed by a BoM (Route: manufacture KIT, both selected ):
- Intermediate1 which is also a BoM (Route: manufacture w 10d Manuf. LT)
- Component1 (Route: buy w 1d Vendor LT)
- Component2 ( Route: buy w 20d Vendor LT)
- Component3 ( Route: buy 20d Vendor LT)
All products have replenishment rules activated and routes properly selected.
Current behaviour: RFQ for the components in the MO only triggered based on Manuf. LT, and do not take into consideration Vendor LT.
Expected behaviour: if Sales Order of Final1 has a delivery date on 25 days time, C2 RFQ should be automatically triggered (and it is only triggered 10 days before Delivery date because on Manuf. LT).
A product (Final1) is composed by a BoM (Route: manufacture KIT, both selected ):
- Intermediate1 which is also a BoM (Route: manufacture w 10d Manuf. LT)
- Component1 (Route: buy w 1d Vendor LT)
- Component2 ( Route: buy w 20d Vendor LT)
- Component3 ( Route: buy 20d Vendor LT)
All products have replenishment rules activated and routes properly selected.
Current behaviour: RFQ for the components in the MO only triggered based on Manuf. LT, and do not take into consideration Vendor LT.
Expected behaviour: if Sales Order of Final1 has a delivery date on 25 days time, C2 RFQ should be automatically triggered (and it is only triggered 10 days before Delivery date because on Manuf. LT).