MS Project Critical Path GANTT Chart

Job ID: 31875701

Budget: $15 – $25 AUD

Hi,

Have created a GANNT Chart and the critical path settings (which should make only CP items red) Some items that are not CP are showing red. Need some advice on how to alter this.
Related categories: Microsoft Project