Electrical Power Engineer need for a small task

Job ID: 33971552

Budget: $14 – $30 NZD

I Need Electrical Power Engineer who cam solve a ac grid problem related to symmetrical / unsymmetrical impedances
its a simple task so quote your final budget because i will inbox only if your budget will be reasonable

translation of task is
Task 3: Synchronous generator with machine transformer (7 points)

The simplified single-pole equivalent circuit diagram applies to a three-phase generator that works via a

transformer on a transmission network with constant voltage and frequency.

Data: All data and calculations in pu (per unit)

Generator:

relative phase-to-phase rotor voltage up = 1.5 pu

relative synchronous reactance xd = 1.2 pu (resistance neglected)

Transformer:

relative combined leakage reactance x-r = 0.15 pu (resistance neglected)

Network:

relative phase-to-phase voltage u, = 1.0 Z0° pu (reference)

relative active power reference pN = 0.63 pu

a) Calculate the phase shift angle a (load angle) between the voltage up and us. What tension precedes? (4 pts)

b) Determine the cosp of the transmission network. Is it inductive or capacitive? (3 pts)