FAT QA/QC Inspector (Electrical and Instrumentation) at the vendor’s facility, Athens, Greece 12.03.2026
I need a seasoned QA/QC professional to carry out a one-day Factory Acceptance Test on a PPC panel at the vendor’s facility, 12 Kerkiras St., Metamorfosi 14452, Athens, Greece. The visit is fixed for 12 March 2026, you must be able to be on-site that day.
You will be looking at both electrical and instrumentation aspects and working to IEC standards. Previous, hands-on FAT experience is essential—I am counting on you to move through the checks efficiently and to spot anything that could later hold up commissioning.
Core objectives while on site
• Verify overall dimensions and construction quality of the panel.
• Cross-check the full Bill of Materials (type, rating, quantity).
• Confirm paint shade and coating thickness meet specification.
• Inspect ferruling and nameplates.
• Compare wiring and functional schemes against the latest drawings, including network connectivity and hardware communication tests.
• Compile photographs, measurement logs, and observations into a concise inspection report the same day (or at most within 24 hours).
I will provide the latest drawings, BOM, and inspection templates in advance. Bring any basic measurement tools you rely on; specialised test equipment for network checks will be available at the vendor’s lab.
If you are confident with IEC-based FATs for electrical and instrumentation panels and can commit to the date, please get in touch and outline similar assignments you have recently completed.
I need a seasoned QA/QC professional to carry out a one-day Factory Acceptance Test on a PPC panel at the vendor’s facility, 12 Kerkiras St., Metamorfosi 14452, Athens, Greece. The visit is fixed for 12 March 2026, you must be able to be on-site that day.
You will be looking at both electrical and instrumentation aspects and working to IEC standards. Previous, hands-on FAT experience is essential—I am counting on you to move through the checks efficiently and to spot anything that could later hold up commissioning.
Core objectives while on site
• Verify overall dimensions and construction quality of the panel.
• Cross-check the full Bill of Materials (type, rating, quantity).
• Confirm paint shade and coating thickness meet specification.
• Inspect ferruling and nameplates.
• Compare wiring and functional schemes against the latest drawings, including network connectivity and hardware communication tests.
• Compile photographs, measurement logs, and observations into a concise inspection report the same day (or at most within 24 hours).
I will provide the latest drawings, BOM, and inspection templates in advance. Bring any basic measurement tools you rely on; specialised test equipment for network checks will be available at the vendor’s lab.
If you are confident with IEC-based FATs for electrical and instrumentation panels and can commit to the date, please get in touch and outline similar assignments you have recently completed.