i need a program and methodology for the following project. Must be finished by 14/08/2025 11 am Eastern Standard time Sydney

You will be engaged to carry out the Constitution Road Infrastructure Upgrade works, which include but are not limited to:

Demolition & Removal

Remove existing kerbs, gutters, footpaths, driveways, and road pavements as shown on the construction drawings.

Sawcut edges to provide clean joints.

Dispose of all waste materials at licensed facilities.

Excavation & Preparation

Excavate to the specified depths for new pavement, kerbs, and footpaths.

Prepare and compact subgrade to the required compaction standards.

Place and compact sub-base and base course materials to achieve design levels.

Concrete Works

Form, pour, and finish new kerbs, gutters, footpaths, pram ramps, and medians in accordance with council specifications.

Place steel reinforcement where required.

Ensure concrete finish, curing, and strength meet specification.

Road Pavement Works

Supply and lay asphalt wearing course and base layers to the required thickness.

Tie in to existing pavements neatly.

Drainage Works

Install new stormwater pits, pipes, and associated drainage infrastructure as shown on the plans.

Connect new drainage to existing networks.

Traffic Management

Supply and implement an approved traffic control plan, maintaining safe pedestrian and vehicle movement during works.

Finishing & Site Restoration

Backfill edges, restore nature strips with topsoil and turf.

Clean site thoroughly and hand over in a safe and operational condition.