Structural Estimation for 5 Sunset Lane
Budget: $30 – $250 USD
I want you to verify to take offs that I had another estimator create, your job is to just check this work below against the attached drawings.
In other words, you are just checking the below information by reviewing the drawing set to verify the accuracy. If you find any errors you just need to highlight the error and put what the correct answer is. The final result will be that all of the lines that are referenced here contain accurate information whether it is a quantity, takeoff, or count. If there is any large item that is missing that you feel needs to be added please add it and indicate in the document that you have done so.
Here is where the document for review begins:
-------------
Referenced Sheets:
S-0: General Structural Notes
S-0.1: Wind Pressure Diagrams
S-0.2: Structural Notes Continued
S-1.0: Foundation Plan
S-1.1: Ground Floor Framing Plan
S-2.0: Second Floor Framing Plan
S-2.1: Roof Framing Plan
S-3.0: Beam Schedule
S-3.1: Column Schedule
S-4.0: Structural Steel Details
S-5.0: Wall Sections and Details
S-6.0: Miscellaneous Details
---
Scope of Work and Quantities
Mobilization and Site Setup (S-0)
Temporary fencing: 400 linear feet
OSHA-compliant barriers and signage
Temporary facilities: site office, sanitation facilities, material storage
Layout and Benchmarking (S-1.0)
Benchmark control points for alignment
Marking for 72 piles, 18 grade beams, 24 columns, and slab edges
Excavation and Trenching (S-1.0)
Excavation for 72 auger-cast piles
Trenches for 18 grade beams and utility crossings
Concrete Piles (S-1.0)
72 auger-cast piles, 14" diameter, 35' deep
Reinforcement: (4) #6 vertical bars, #3 ties @ 12" O.C. in the top 14'
Pile Caps (S-1.1)
PC-1: 20 occurrences, 4'-0" x 2'-4", (3) #6 bars each way, top and bottom
PC-2: 6 occurrences, 8'-0" x 4'-0", (6) #6 bars each way, top and bottom
Grade Beams (S-1.1)
GB-1: 18 occurrences, 16" x 24", (3) #5 top/mid/bottom, #3 stirrups @ 10" O.C.
GB-2: 12 occurrences, 24" x 24", (3) #6 top/mid/bottom, #3 stirrups @ 9" O.C.
GB-3: 8 occurrences, 12" x 12", (2) #5 top/mid/bottom, #3 stirrups @ 24" O.C.
Ground Floor Slab (S-1.1)
3,500 sq. ft., 6" reinforced concrete slab
Vapor barrier: 6-mil polyethylene
Control joints installed as specified
Second Floor Slab (S-2.0)
2,800 sq. ft., 6" suspended reinforced concrete slab
Embedded MEP sleeves: 50 total
Temporary shoring during curing phase
Balcony Slabs (S-2.1)
550 sq. ft. total
Waterproof membrane and drainage outlets
Concrete Beams (S-3.0)
B100: 8"x12", 14 occurrences, (2) #5 top/bottom, #3 stirrups @ 12" O.C.
B101: 12"x24", 10 occurrences, (2) #5 top/bottom, #3 stirrups @ 12" O.C.
Tie Beams (T-A): 8"x12", 22 occurrences, (2) #5 top/bottom, #3 stirrups @ 12" O.C.
Concrete Columns (S-3.1)
8"x12": 12 occurrences, (4) #5 vertical bars, #3 ties @ 8" O.C.
12"x12": 8 occurrences, (4) #6 vertical bars, #3 ties @ 12" O.C.
12"x24": 4 occurrences, (8) #6 vertical bars, #3 ties @ 12" O.C.
Structural Steel (S-4.0)
W12x152, W14x257, W8x35 Beams: 6 total
HSS Columns: 4"x4"x1/4", 6"x6"x1/2": 8 total
Includes plates, welded and bolted connections
Embedded Hardware (S-4.0)
Anchor bolts: 150 total
Base plates: 18 total
Embedded dowels and conduits: 50 total
Waterproofing and Sealants (S-6.0)
Waterproof membranes: 1,200 sq. ft. coverage
Joint sealants: 800 linear feet
Inspections and Testing (S-6.0)
Compression tests: 10 tests
Concrete cylinder tests: 20 tests
Pile load tests: 5 tests
Final Site Cleanup (S-6.0)
Removal of temporary facilities
Final grading and restorations
In other words, you are just checking the below information by reviewing the drawing set to verify the accuracy. If you find any errors you just need to highlight the error and put what the correct answer is. The final result will be that all of the lines that are referenced here contain accurate information whether it is a quantity, takeoff, or count. If there is any large item that is missing that you feel needs to be added please add it and indicate in the document that you have done so.
Here is where the document for review begins:
-------------
Referenced Sheets:
S-0: General Structural Notes
S-0.1: Wind Pressure Diagrams
S-0.2: Structural Notes Continued
S-1.0: Foundation Plan
S-1.1: Ground Floor Framing Plan
S-2.0: Second Floor Framing Plan
S-2.1: Roof Framing Plan
S-3.0: Beam Schedule
S-3.1: Column Schedule
S-4.0: Structural Steel Details
S-5.0: Wall Sections and Details
S-6.0: Miscellaneous Details
---
Scope of Work and Quantities
Mobilization and Site Setup (S-0)
Temporary fencing: 400 linear feet
OSHA-compliant barriers and signage
Temporary facilities: site office, sanitation facilities, material storage
Layout and Benchmarking (S-1.0)
Benchmark control points for alignment
Marking for 72 piles, 18 grade beams, 24 columns, and slab edges
Excavation and Trenching (S-1.0)
Excavation for 72 auger-cast piles
Trenches for 18 grade beams and utility crossings
Concrete Piles (S-1.0)
72 auger-cast piles, 14" diameter, 35' deep
Reinforcement: (4) #6 vertical bars, #3 ties @ 12" O.C. in the top 14'
Pile Caps (S-1.1)
PC-1: 20 occurrences, 4'-0" x 2'-4", (3) #6 bars each way, top and bottom
PC-2: 6 occurrences, 8'-0" x 4'-0", (6) #6 bars each way, top and bottom
Grade Beams (S-1.1)
GB-1: 18 occurrences, 16" x 24", (3) #5 top/mid/bottom, #3 stirrups @ 10" O.C.
GB-2: 12 occurrences, 24" x 24", (3) #6 top/mid/bottom, #3 stirrups @ 9" O.C.
GB-3: 8 occurrences, 12" x 12", (2) #5 top/mid/bottom, #3 stirrups @ 24" O.C.
Ground Floor Slab (S-1.1)
3,500 sq. ft., 6" reinforced concrete slab
Vapor barrier: 6-mil polyethylene
Control joints installed as specified
Second Floor Slab (S-2.0)
2,800 sq. ft., 6" suspended reinforced concrete slab
Embedded MEP sleeves: 50 total
Temporary shoring during curing phase
Balcony Slabs (S-2.1)
550 sq. ft. total
Waterproof membrane and drainage outlets
Concrete Beams (S-3.0)
B100: 8"x12", 14 occurrences, (2) #5 top/bottom, #3 stirrups @ 12" O.C.
B101: 12"x24", 10 occurrences, (2) #5 top/bottom, #3 stirrups @ 12" O.C.
Tie Beams (T-A): 8"x12", 22 occurrences, (2) #5 top/bottom, #3 stirrups @ 12" O.C.
Concrete Columns (S-3.1)
8"x12": 12 occurrences, (4) #5 vertical bars, #3 ties @ 8" O.C.
12"x12": 8 occurrences, (4) #6 vertical bars, #3 ties @ 12" O.C.
12"x24": 4 occurrences, (8) #6 vertical bars, #3 ties @ 12" O.C.
Structural Steel (S-4.0)
W12x152, W14x257, W8x35 Beams: 6 total
HSS Columns: 4"x4"x1/4", 6"x6"x1/2": 8 total
Includes plates, welded and bolted connections
Embedded Hardware (S-4.0)
Anchor bolts: 150 total
Base plates: 18 total
Embedded dowels and conduits: 50 total
Waterproofing and Sealants (S-6.0)
Waterproof membranes: 1,200 sq. ft. coverage
Joint sealants: 800 linear feet
Inspections and Testing (S-6.0)
Compression tests: 10 tests
Concrete cylinder tests: 20 tests
Pile load tests: 5 tests
Final Site Cleanup (S-6.0)
Removal of temporary facilities
Final grading and restorations
Related categories:
Engineering
Building Architecture
Civil Engineering
Structural Engineering
AutoCAD