ARUN update to Storm Water control plan
Budget: $30 – $250 USD
$100. (ignore mandatory range estimate in freelancer)
1 Update impervious pervious sf and consequent percentages, and consequent calculations
2 Fix contents index page number references – pages have been removed
3 Remember that there are two separate source documents. 4445. 4647
4 Clearly label catchment areas in large font size -You can use updated C3 no need to recreate it 5 include C3 sheet in word/pdf doc
6 Re calculate/calculate proportionality, volume etc of volume to a bio retention, b volume to gutter and down to Coleman Drive and out. Note some of the new roadway drainage gets down to the bio swale through a downspout etc close to the tunnel
7 Statement in the report conforming to page 5 and 6 with detail, for bio retention –“Small and single family home project” not necessary to review other parts of this template
Other small updates as needed
1 Update impervious pervious sf and consequent percentages, and consequent calculations
2 Fix contents index page number references – pages have been removed
3 Remember that there are two separate source documents. 4445. 4647
4 Clearly label catchment areas in large font size -You can use updated C3 no need to recreate it 5 include C3 sheet in word/pdf doc
6 Re calculate/calculate proportionality, volume etc of volume to a bio retention, b volume to gutter and down to Coleman Drive and out. Note some of the new roadway drainage gets down to the bio swale through a downspout etc close to the tunnel
7 Statement in the report conforming to page 5 and 6 with detail, for bio retention –“Small and single family home project” not necessary to review other parts of this template
Other small updates as needed