7578 Brown Bridge alterations
Budget: $750 – $1,500 USD
Scope and goal of requested alterations is to have a complete set of prints ready to submit to Grand Traverse County Building dept.
1. Add elevations that are missing
2. Add foundation drawing Indicate all point load and load bearing walls.
3. Change from SIP roof to conventional trusses for all but the great room and kitchen
4. Details of point loads and connections where required
5. Soil bearing capacity must be on drawings for sandy soils
6. Show the required connections from timber trusses and SIP panels to foundation or walls
7. Verify attached local design criteria has been met
8. Braced wall lines and design
1. Add elevations that are missing
2. Add foundation drawing Indicate all point load and load bearing walls.
3. Change from SIP roof to conventional trusses for all but the great room and kitchen
4. Details of point loads and connections where required
5. Soil bearing capacity must be on drawings for sandy soils
6. Show the required connections from timber trusses and SIP panels to foundation or walls
7. Verify attached local design criteria has been met
8. Braced wall lines and design